2021 | ||
MONTH | DESCRIPTION | AMOUNT(Rs) (in Million) |
---|---|---|
Jan - Nov 21 | MANDO - 110KV SWITCHYARD ELECTRICAL WORKS - THENNUR CASTING PLANT | 95.26 |
Mar 21 - Mar 22 | MANDO - CIVIL AND PEB WORKS - THENNUR CASTING PLANT | 415.00 |
Mar 21 - Sep 21 | ENGINE SHOP # 2 3C MIP LINE MACHINE UNLOADING ACTIVITY (KAPPA PE 1.2) | 25 |
Mar 21 - May 22 | HMIE - STEEL STRUCTURE WORKS - HYUNDIA MOTOR - GURGAON | 289.80 |
Apr 21 - Mar 22 | KIA - LANDSCAPING WORKS | 36 |
Jun 21 - Dec 21 | DKD PROJECT | 44 |
Jul 21 - Jan 22 | MANDO - MEP WORKS & ELECTRICAL WORKS - THENNUR CASTING PLANT | 150.00 |
Aug 21 - May 23 | MHMIE - ELECTRICAL WORKS # 2 - HYUNDIA MOTOR - GURGAON | 286.00 |
Aug 21 - May 22 | KIA BODY SHOP EXHPASION - ARCHITECTURE AND CIVIL WORKS | 22.00 |
Aug 21 - Mar 22 | PIO CANTEEN WORKS - RC & FINISHING WORKS | 25.00 |
2020 | ||
MONTH | DESCRIPTION | AMOUNT(Rs) (in Million) |
---|---|---|
Jan - Dec 20 | Hyundai DKD - Project | 12.99 |
Mar 20 - Jan 21 | HMIE - ANNEX -HYDERABAD - MECHANICAL & ELECTRICAL WORKS | 69.80 |
Jul - Aug 20 | GLOVIS PENUKONDA CIVIL,STRUCTURE & ELECTRICAL WORKS | 51.00 |
Jun 20 - Feb 21 | HMI Facility Improvement Works | 37 |
2019 | ||
MONTH | DESCRIPTION | AMOUNT(Rs) (in Million) |
---|---|---|
Jan - Dec 19 | Hyundai DKD - Project | 191.22 |
Jan 19 - Mar 20 | HYUNDAI GLOVIS - CHENNAI CKD - CIVIL,RC,ARCHITURE & LANDSCPING WORK | 287 |
Jan 19 - Mar 20 | MOBIS- CHENNAI - MEB / MDPS PROJECT | 79.90 |
Apr 19 - Nov 20 | HEIPL - Chennai - Steel Scrap yard Works - Phase # 2 | 191.09 |
Apr 19 - Jun 20 | New Rain water pond Civil,Electrical & Mechanical | 94.60 |
Sep 19 - Oct 20 | MOBIS - CHENNAI PDC STRUTURE,ELECTRICAL,MECHANICAL | 232.00 |
2018 | ||
MONTH | DESCRIPTION | AMOUNT(Rs) (in Million) |
---|---|---|
Jan - Dec 18 | Hyundai DKD - Project | 670.90 |
Mar 18 - Jun 19 | KIA - ELECTRICAL WORKS | 684.63 |
Apr 18 - Dec 19 | HMI - GURGAON - RC WORKS | 497.12 |
Jul 18 - Feb 21 | HMI - GURGAON - ELECTRICAL WORKS | 322.50 |
Dec 18 - Jan 20 | SUNGWOO SSP # 2 - CHENNAI | 190 |
Dec 18 - Jan 20 | SUNGWOO SHI - CANTEEN RENOVATION WORK - CHENNAI | 190 |
2017 | ||
MONTH | DESCRIPTION | AMOUNT(Rs) (in Million) |
---|---|---|
Jan - Mar 17 | Hyundai - Body Shop Line Improvement Works | 18.00 |
Jan - Mar 17 | Hyundai - Engine Shop Machine Shifting& Utility | 20.00 |
Jan - Mar 17 | Hyundai - Electrical Improvement Works | 25.00 |
Jan - Apr 17 | Hyundai - Roof Sheet - All Shops | 25.00 |
Feb 17 | Hyundai - Panel Room Sheeting Works - All Shops | 5.00 |
Mar 17 | Hyundai - Vietnam CKD Project | 139.00 |
Mar 17 | NHVS - VIZAG | 117.00 |
Apr 17 | Hyundai - Air Washer Mechanical Works | 4.00 |
Jan - May 17 | Hyundai DKD - Project | 166.00 |
May 17 | Hyundai - Engine Shop Machine Shifting & Utility | 6.00 |
May 17 | Hyundai Test Track Asphalting Works | 8.00 |
May 17 | HEC - Hyundai WIA Civil Works | 6.00 |
Jun - Dec 17 | Hyundai DKD - Project | 738.76 |
Aug 17 - Jul 19 | KIA - CIVIL,RC,ARCHITECTURE & LANDSCAPING WORKS | 2,333.06 |
Nov 17 - Feb 19 | KIA - MECHANICAL WORKS | 349.77 |
2016 | ||
MONTH | DESCRIPTION | AMOUNT(Rs) (in Million) |
---|---|---|
Jan 16 | Hyundai Container Yard Area Paver Block Laying Works | 14.98 |
Mar 16 | Hyundai DKD - Project | 6.20 |
Mar 16 | Hanil DG Electrical Work | 2.20 |
Mar 16 | Mobis Election Works | 6.90 |
Apr 16 | Hyundai Asphalt Laying Work inbetween PDI Exit Repair Shop | 6.68 |
May 16 | Hyundai Sewage Treatment Plant ( 720 KLD) Civil Works | 14.61 |
May 16 | Hyundai Paint Shop # 2 New Chiller Electrical Works | 3.72 |
May 16 | Hyundai Test Track # 1 Rough Road Modification Civil Works | 5.98 |
May 16 | Hyundai Engine Shop Machine Installation Works | 7.80 |
May 16 | Hyundai DKD - Project Xcent | 5.26 |
Jun 16 | Hyundai Welfare Center Renovation Works | 20.00 |
Aug - Dec 16 | Hyundai DKD - Project | 173.00 |
Sep 16 | Hyundai - Welfare Center (Gym Building) | 25.00 |
Aug - Dec 16 | Hyundai - Rain Water Line Works | 19.00 |
Oct 16 | Hyundai Engine Shop Machine Installation Works | 10.00 |
Dec 16 | Hyundai - Farm House Works | 4.00 |
2015 | ||
MONTH | DESCRIPTION | AMOUNT(Rs) (in Million) |
---|---|---|
Mar 15 | Civil Works For Mobis Ware House Works - Mumbai - Loa Dt.18.03.2014, Period - 18.03 to 15.07.2015 | 137.63 |
Mar 15 | Hyundai Engine Shop # 1 E1 Mx1 Crank Line Machine Removal & Scraping Works | 4.94 |
Jun 15 | Hyundai Trans Mission # 1Machine Shifting TM# 1 Aging Project Phase M/X Shifting & Installation ( New Machines) | 2.49 |
Aug 15 | Hyundai Test Track # 2 Asphalt Laying Work | 33.44 |
Aug 15 | Hyundai Engine Shop # 1 Line Machine Removal Works | 6.30 |
Oct 15 | Hyundai DKD - Project | 31.16 |
Jun 15 | Hanil Auto - Dongkwang Construction | 99.60 |
Nov 15 | Hyundai Crusher Run For New Car Parking Civil Works | 49.06 |
Nov - Dec 15 | Hyundai - All Shops Mechanical Works | 8.40 |
Apr - Dec 15 | Hyundai - All Shops Electrical Works | 15.00 |
Dec 15 | Hyundai DKD - Project | 5.88 |
2014 | ||
MONTH | DESCRIPTION | AMOUNT(Rs) (in Million) |
---|---|---|
Apr 14 | Renault - Nissan Works | 2.49 |
May 14 | Mobis - Asphalt Road Repair Works - Mobis Audio / Airbag Remodeling Project, 02.05.2014 to 05.06.2014- PB.10%, MBG-5% | 8.40 |
Jul 14 | Lotte - Mechanical Works - Lech-SC-0003 7th July 2014 - February 2015 | 58.80 |
Oct 14 | Electrical & Mechanical Works for Mobis West Unit Project - Mumbai - Loa Dt. 21.10.2014, Period - 21.10.14 to 15.07.2015 | 64.70 |
Nov 14 | Annex-Civil Works For Mobis West Unit Project- Mumbai - Loa Dt.17.11.2014, Agree.Dt.8.12.2014, Period - 06.12.14 to 15.07.15 | 54.80 |
Nov 14 | Mobis - Hyderabad - Electrical & Mechanical Works for Mobis Hyderabad R &D Project - Loa Dt.03.11.2014,Agree Dt.04.12.2014, Period - 03.11.2014 to 28.02.2015 40436618,29045339,69481) | 69.55 |
Dec 14 | Lotte - \Utility Mechanical Works - 2 -Loi -23.12.2014 | 99.00 |
2013 | ||
MONTH | DESCRIPTION | AMOUNT(Rs) (in Million) |
---|---|---|
Feb 13 | Hyundai WIA - Electrical Works for Hyundai WIA CVJ Factory Project | 78.53 |
Feb 13 | Hyundai WIA - Land Levelling and Fence Work | 9.33 |
May 13 | Mobis - Secondary Factory - Civil Works | 160.00 |
Jun 13 | Mobis - Secondary Factory - Electrical Works | 116.00 |
Sep 13 | Hyundai - Renovation Work For Hyundai Director's Office | 39.13 |
Nov 13 | Mobis - Electrical Works For Mobis Audio / Airbag Remodeling Project Loa Dt.26th November 2013, 10.06.13 TO 30.04.14 - PB.10%, MBG-5% | 97.80 |
2012 | ||
MONTH | DESCRIPTION | AMOUNT(Rs) (in Million) |
---|---|---|
Feb 12 | Hyundai Motor India -Car Parking Yard Concrete Flooring Near Test Track-II | 39.17 |
Mar 12 | Hyundai Motor India -Car Parking Yard Concrete Flooring Near AL Foundry-II | 22.37 |
May 12 | Jintech - Electrical Works | 13.48 |
Sep 12 | 765kv-Tr 330mva, Bina S/S Project - Hyundai Heavy Industries (HHI) | 93.00 |
Sep 12 | Hyundai Motor India - HMI Press #2 Back Side Pallet Storage Yard(38 X 70)200mm Thick | 17.32 |
Sep 12 | Renault - Nissan - Supply of Line #2 Conveyor in Trim and Chassis Shop | 3.93 |
Dec 12 | Doosan - Remodelling Works - Mechanical & Electrical Works | 12.50 |
Dec 12 | Hyundai WIA - Civil Works For Hyundai WIA CVJ Factory Project | 30.17 |
2011 | ||
MONTH | DESCRIPTION | AMOUNT(Rs) (in Million) |
---|---|---|
Jan 11 | Mando India Steering - Construction Project for Mando India Steering Systems | 75.05 |
Jan 11 | Ford India Pvt Ltd - IR Air Balancer Structure Dismantling and Shifting | 0.04 |
Jan 11 | Ford India Pvt Ltd - Supply, Installation & Commng B299 Structural Work Ed Line | 0.67 |
Jan 11 | Ford India Pvt Ltd - Dismantling Charges PH1 Eng Plant | 1.97 |
Jan 11 | Hyundai Amco - Electrical Work HMI VVIP Visit Preparation Work in Chennai | 0.30 |
Jan 11 | Hyundai Amco - Civil Work For HMI Engine Shop #3 | 45.00 |
Feb 11 | Ford India Pvt Ltd - Coolant Tank For Head & Block Machining-Ford Project | 4.86 |
Mar 11 | Renault - Nissan - Modification Of Existing Conveyor For 36 JPH AT T&C Shop | 0.11 |
Mar 11 | Ford India Pvt Ltd - Unloading/Positioning at C/V Dressline Expn | 0.18 |
Apr 11 | Hyundai Motor India -Construction Of New Wheel Alignment | 2.29 |
Apr 11 | Ford India Pvt Ltd - Installation and Comissioning of Cooling Tower FRP Model | 1.38 |
Apr 11 | Hyundai Amco - HMI #2 Press Shop Project | 54.23 |
May 11 | Hyundai Amco - Electrical Work for HMI #2 Press Shop Project | 49.75 |
May 11 | Hyundai Motor India -Fabrication and Supply of Body Steel Pallet-DKD Project | 2.17 |
May 11 | Hyundai Motor India -Demolition Work of Bumper Shop | 5.70 |
May 11 | Hyundai Motor India -DKD Dismantling Project | 1.55 |
May 11 | Renault - Nissan - Installation and Commisioning of Line #2 Conveyors for Body Shop | 1.70 |
May 11 | Ford India Pvt Ltd - Piping Works for Coolant | 7.09 |
May 11 | Hyundai Amco - (Electrical Works) HMI#2 Press Shop Project | 49.75 |
May 11 | Hyundai Amco - Supply and Serice of Mechnical and Electrical Works,Construction Equiptment with Fuel | 20.75 |
Jun 11 | Hyundai Motor India -Truss Inforcement for Chasis in Bumper Paint Shop | 4.10 |
Jun 11 | Hyundai Motor India -T1 Case Housing Machine Shifting Works | 1.33 |
Jun 11 | Hyundai Motor India -T2 Case Housing Machine Shifting Works | 1.23 |
Jun 11 | Hyundai Motor India -Fabrication and Supply of Body Steel Pallet-DKD Project | 3.13 |
Jun 11 | Federal Mogul - Friction Plant Chennai | 86.69 |
Jun 11 | Renault - Nissan - Supply of Line #2 Conveyor in Trim and Chassis Shop | 6.00 |
Jun 11 | Renault - Nissan - Supply of Line #2 Conveyors for Body Shop | 0.80 |
Jun 11 | Renault - Nissan - Installation and Commissioning of X 11m Conveyor in Trim and Chasis | 0.05 |
Jun 11 | Renault - Nissan - Installation and Commisioning of H 79 Conveyor in Trim and Chassis Shop | 0.40 |
Jul 11 | Ford India Pvt Ltd - Mezzanine for Tyre Storage-Wheels India | 4.94 |
Jun 11 | Ford India Pvt Ltd - Dismantling Weld Mesh from Phase 1 and Installation of Phase 1 to Phase 3 | 0.09 |
Jun 11 | Doosan - Substation Works for Doosan Chennai Works Extension Process | 145.23 |
Jun 11 | Doosan - Remodelling the Existing Office | 2.26 |
Jun 11 | Doosan - Civil and Infrastructure Works | 209.98 |
Jun 11 | Hyundai Amco - Supply of Pare Lamps for Garden & BLDG Light Fittings at Hyundai Directors Residence | 0.02 |
Jun 11 | Hyundai Motor India -Fabrication and Supply of Body Steel Pallet-DKD Project | 2.11 |
Jun 11 | Ford India Pvt Ltd - Supply and Installation of Comp.Air & RO Water Line/160k EXPN in Eng Plant | 1.47 |
Aug 11 | Hyundai Motor India -Fabrication and Supply of Body Steel Pallet-DKD Project | 1.02 |
Aug 11 | Mando India Steering - Electrical and Mechanical Work as per Quation Attached | 13.77 |
Aug 11 | Ford India Pvt Ltd - Construction of Cast Storage,Assy Market Place & Culvert | 54.75 |
Aug 11 | Ford India Pvt Ltd - Structural & Civil Work for IP Mezzanine | 27.12 |
Aug 11 | Ford India Pvt Ltd - Structural Work 160k EXPN in Eng Plant | 6.79 |
Aug 11 | Hyundai Amco - (Steel Structure Work 4)HMI#2 Press Shop Project | 3.81 |
Sep 11 | Hyundai Motor India -Electrical Works at Paint Shop #1 (Power Pannel Works) | 1.49 |
Sep 11 | Federal Mogul Piping Works Supply,Erection,Commissioing & Testing | 5.02 |
Sep 11 | Renault - Nissan - Installation and Commisioning of Line #2 Conveyors in Trim and Chasis Shop | 14.71 |
Sep 11 | Ford India Pvt Ltd - Pilot Building Area Relocation | 0.61 |
Oct 11 | Hyundai Motor India -Construction of New Canopy Buliding | 8.81 |
Oct 11 | Doosan - Mechanical and Electrical Work of Factory at Doosan Chennai | 167.00 |
Oct 11 | Hyundai Amco - Carryout The Sound Proof Pannel Construction Work a Hyundai Diretors Office | 1.86 |
Nov 11 | Posco - Temporary Electrical Work - Posco | 33.95 |
Nov 11 | Posco - Electrical Construction Work ( Package 2) - India Posco-Maharashtra CRM Project | 148.39 |
Nov 11 | Doosan - Preliminary Works for Painting Shop for Doosan Chennai Works Extension Process | 6.93 |
Nov 11 | Hyundai Amco - Temporary Work for Engine Shop #3 | 13.38 |
Nov 11 | Hyundai Motor India -Fabrication and Supply of Body Steel Pallet-Dkd Project | 3.83 |
Dec 11 | Hyundai Motor India -New Car Parkng Yard Between Car Parking Yard & Test Track-II | 20.87 |
Dec 11 | Doosan - Infrastructure Development - DCW Extension - Mannur | 209.98 |
2010 | ||
MONTH | DESCRIPTION | AMOUNT(Rs) (in Million) |
---|---|---|
01-Jan | Steel Pallets For DKD Operations | 76.80 |
10-Jan | Concrete Flooring and Construction Work at Propane Yard | 4.43 |
15-Feb | Overhead Conveyor Deck Fabrication Works | 3.42 |
16-Mar | Car & Two Wheeler Parking ( Area 325 Sqm) - Civil Works | 1.52 |
06-Apr | Lift & Shift Of DV Mcs For PH3 Eng Assy Line | 5.73 |
12-Apr | Engine Shop # 1 Central Coolant System Shifting Works | 2.43 |
03-May | Airwasher Ventilation Ducting - Assembly # 1 | 2.12 |
07-May | Truss Reinforcement In Engine Assy Area | 1.36 |
11-May | Machine Shifting Charges Gauge Change for Crank Line | 1.50 |
13-May | IE20C - E2 - Cylinder Head Line - HA Project - Retooling Works | 1.49 |
17-May | Weigh Bridge Works (Weigh Bridge, Civil Works,Piping & Electrical | 1.22 |
21-May | Fire Hydrant System - Paint Shop2 | 1.10 |
03-Jun | Final Tester Machine Additional Works | 2.04 |
04-Jun | Airwasher Ventilation Ducting - Assembly # 1 | 1.89 |
09-Jul | Trim Line & Final Line Assy Civil Works | 1.34 |
24-Jul | Construction Of Air Reciever Foundation At Behind Comp Plant # 2 , Inbetween Assy # 2 & Eng # 2 | 4.86 |
16-Aug | Epsi lon-3 Cylinder Assy Improvement Works | 6.50 |
19-Aug | Flowmeter Utility Works - 5 Areas | 1.34 |
29-Aug | HMP - SRTC Building - Civil Works | 18.09 |
01-Sep | RBI Pallets For Press Shop | 8.40 |
21-Dec | Ford India Ltd - Unloading & Positioning - Sigma Machines for Phase3 | 8.69 |
2009 | ||
MONTH | DESCRIPTION | AMOUNT(Rs) (in Million) |
---|---|---|
03-Mar | Renault Nissan Body Tcf Conveyor Local Portion Mfg & Installation | 29.50 |
20-Mar | Ford - Engine Shop Crane Structural Works | 15.00 |
20-Mar | Ford - Engine Shop Machine Shifting Works | 12.30 |
30-Apr | Nissan - Gun Line Installation Works | 15.00 |
11-Aug | Ford - Utility Works | 28.00 |
11-Sep | DKD Pallets- Hyundai Motor India Ltd. | 8.00 |
09-Oct | GTA Building - Hyundai Motor India Ltd. | 8.20 |
10-Nov | Lotte India Foods Electrical Works | 105.00 |
12-Dec | Ford - Unloading And Positioning-Sigma Machines F/PH3 | 123.00 |
2008 | ||
MONTH | DESCRIPTION | AMOUNT(Rs) (in Million) |
---|---|---|
19-Jan | TCF Shop Conveyor Project - tata Motors Limited, Kolkatta | 30.00 |
03-Mar | Hyundai Construction Equipment India Pvt Limited, Pune | 93.00 |
14-Apr | Car Parking Area Civil Works - Engine Shop Phase Ii -Hmil | 22.00 |
14-May | Boiler House Civil Works - Hmil | 14.00 |
19-May | D.K.D For Hyundai Motor India Limited - 800 Cars/Month (Malaysia) | 240.00 |
20-Jun | Jintech Factory - Pondur Site | 35.50 |
12-Jul | Car Parking Area - Civil Works | 19.40 |
23-Jul | Ford C195 & B376 Relocation Works - Body Shop | 15.00 |
20-Aug | Bus Parking Area - Mechanical Works | 12.00 |
15-Sep | Paint Shop Revamping Works | 22.00 |
19-Sep | Lotte Confectionery Ltd - Nemam Factory Electrification | 150.00 |
16-Nov | Bus Parking Area - Civil Works | 74.00 |
12-Dec | C & C - Hyundai - Electrical Works | 40.00 |
2007 | ||
MONTH | DESCRIPTION | AMOUNT(Rs) (in Million) |
---|---|---|
30-Apr | Engine Shop Electrical Works | 95.00 |
10-May | HMIE Building Construction - Civil Works - 1 | 62.86 |
21-May | Aluminum Foundry Shop - Mechanical Works | 86.10 |
06-Jun | Hyundai Press Shop Pallets | 30.20 |
20-Jun | HMIE Building Construction - Civil Works - 2 | 40.28 |
07-Jul | Engine Shop Decker Works - # 2 - Hyundai | 20.90 |
24-Jul | Jintech Factory At Hanil Automotive Site | 12.00 |
24-Aug | Hwashin Expansion Works | 31.60 |
20-Oct | Tata Small Car Project Conveyor Systems - HHI at Kolkatta | 27.30 |
12-Dec | Dong Woo Machine Shifting Project From HMIL | 6.00 |
16-Dec | Body Shop And Engine Tm Shutdown Works for Pb Project | 18.00 |
2006 | ||
MONTH | DESCRIPTION | AMOUNT(Rs) (in Million) |
---|---|---|
10-Jan | Car Parking Area | 55.00 |
10-Jan | Container Yard | 23.00 |
10-Jan | Main Contract HMI 2nd Factory Yard | 49.60 |
25-Jan | Press Shop Expansion Works - Electrical | 38.80 |
05-Jun | Paint Shop Expansion Works - Mechanical | 91.40 |
15-Jun | Body Shop Expansion Works - Electrical | 93.50 |
05-Jul | Utility Building Works | 12.00 |
25-Jul | Street Light Pole Works | 14.35 |
10-Aug | Mobis Module Plant Electrical Works | 51.00 |
15-Aug | PDI Expansion Repair Shop | 23.20 |
19-Sep | Pipe Rack Project Works | 54.60 |
25-Sep | Additional Works - HMI expansion | 19.30 |
05-Nov | Assembly Shop Lighting Structure | 20.00 |
2005 | ||
MONTH | DESCRIPTION | AMOUNT(Rs) (in Million) |
---|---|---|
30-Apr | VVIP Visit Electrical | 12.00 |
08-Jul | New PDI Car Parking Area Jungle Clearance Works | 19.00 |
08-Jul | New PDI Car Parking Fencing Work | 39.00 |
08-Aug | Welfare Centre Piping Rectification Works | - |
16-Aug | Hyundai Expansion Phase - II Civil Works | 767.00 |
23-Dec | Mechanical Works - Bumper Shop Facility Imp | 24.00 |
2004 | ||
MONTH | DESCRIPTION | AMOUNT(Rs) (in Million) |
---|---|---|
26-May | Container Yard Civil Works | 13.00 |
24-Aug | Lighting Structure, Recycling Platform, Electrical Works | 11.00 |
10-Sep | Electrical Works - Various Shops | 13.30 |
10-Oct | Civil Works, Electrical Works Ware House Utility Works & Wbs Mezannine Extension | 12.00 |
18-Oct | PDI Car Parking Area Civil Works | 15.00 |
2003 | ||
MONTH | DESCRIPTION | AMOUNT(Rs) (in Million) |
---|---|---|
04-Apr | Electrical & mechanical works - Hwashin | 35.00 |
14-Aug | Old PDI Car parking - civil work | 50.00 |
01-Sep | Utility works - JBM sungwoo | 12.00 |
23-Sep | Main facility extension | 130.00 |
26-Dec | Labour Charges For Structural Steel Works | 65.00 |
2002 | ||
MONTH | DESCRIPTION | AMOUNT(Rs) (in Million) |
---|---|---|
20-Aug | Paint shop H1 conveyor expansion | 72.00 |
26-Dec | Assembly shop conveyor | 109.00 |
2001 | ||
MONTH | DESCRIPTION | AMOUNT(Rs) (in Million) |
---|---|---|
22-Feb | Completed ducting work for new bumper paint shop at Hyundai Motor India ltd. | 15.00 |
28-Dec | Change of name of Cheong Song Autotech India Pvt. Ltd to Inkor Autotech India pvt. Ltd. | - |
1999 | ||
MONTH | DESCRIPTION | AMOUNT(Rs) (in Million) |
---|---|---|
24-Jun | Started manufacture of fabrication of steel pallets for Ford India ltd. | - |
06-Nov | Completed plumbing work of GMR plant | - |
19-Nov | Completed fabrication work of GMR plant | - |
21-Nov | Completed power project of GMR plant | - |
1998 | ||
MONTH | DESCRIPTION | AMOUNT(Rs) (in Million) |
---|---|---|
10-Mar | Started pallet production for Hyundai motor India Ltd. | 20.00 |
30-Jun | Completed electrification work in Hyundai motor India Ltd. | 12.00 |
1997 | ||
MONTH | DESCRIPTION | AMOUNT(Rs) (in Million) |
---|---|---|
07-Jul | Established Cheong Song Autotech India Pvt. Ltd. | - |
09-Sep | Obtained ESA license | - |
15-Oct | Received GMR power plant plumbing, fabrication and electrification contract of HHEC | 25.00 |